Work is beginning on Davis Crescent today to widen the footpath on the western side and install a pedestrian crossing across Short Street near Lumsden Green. Construction is expected to take six weeks and the project will be delivered in stages to minimise disruption for businesses and impacts on car parking. Please note that the dates for these stages are subject to change.
The official notification of works from AT is available to view here.

Stage 1: 29 April – 12 May 2024
Stage 2: 13 May – 28 May 2024
Stage 3: 29 May – 10 June 2024
Traffic will continue to travel in both directions during the project. Please note that on-street parking on Kingdon Street, Carlton Gore Road, and in front of Urbano Interiors will not be impacted. Off-street parking is also available nearby. Please see the attachment linked here, showing the work area for each stage.